Kenya Large Pond Remediation Works

Embankment Liner

The 3-week project involved the installation of 14,546m2 Coletanche ES 4 bituminous geomembrane liner as erosion control on the embankment in five lots. Kenya Pond was previously unlined and windy conditions had resulted in 1.7 km of embankment being steadily eroded by waves. 

Shamrock Civil and DDT Liners established a strong working relationship on the project and look forward to working together in the future.

Client
QGC
Contractor
Shamrock Civil under a Design & Construct contract with Red Earth Engineering
Project Value
Timeframe
3 Weeks (Feb-March)
Workforce
9